Amager Beach_Haslov and Kjaersgaard Planners and Architects

Landscape Architecture: Haslov and Kjaersgaard Planners and Architects
Construction period: 18 months.
1.5 mills. cubic metres of raw material has been used for the construction of the beach.
Overall area: 346.000m2
Dimension north-south: 2.9km
Beach width: Generally 50m.
Terrain: Elev. Generally +1.4m Dunes up to +3.5m.
Distance to downtown: 5km. Users up to 40.000/day Population 1.500.000 within 10-12km
Parking: 333 permanent and a further 667 non permanent.
Price: 33 mill. Euros
Text, photos: HOGK
Previous State

Landscape Architecture: Haslov and Kjaersgaard Planners and Architects
Construction period: 18 months.
1.5 mills. cubic metres of raw material has been used for the construction of the beach.
Overall area: 346.000m2
Dimension north-south: 2.9km
Beach width: Generally 50m.
Terrain: Elev. Generally +1.4m Dunes up to +3.5m.
Distance to downtown: 5km. Users up to 40.000/day Population 1.500.000 within 10-12km
Parking: 333 permanent and a further 667 non permanent.
Price: 33 mill. Euros
Text, photos: HOGK
Previous State
The east coast of Amager, an independent part of Copenhagen, south of the city centre was used for landfill during the 1930 ́ties. An artificial beach was established despite the local conditions with very shallow water. The layout was simple: Sand was held in by means of wooden railing. The western part of the beach was laid out as a lawn-like park area along the coastal road, placed parallel to the coast. During the 1990’ies the development of the area started south and north of the beachpark.

Aim of the Intervention
Amager Beach Park has been one of the largest urban recreational development projects, close to the city centre of Copenhagen. The beach park has transformed the coastal landscape of the city and the island of Amager facing the Sound. The new Amager Beach is designed to be a very special place in the city: a large-scale landscape that provides a contrast to the density of the Copenhagen waterfront. The open sky and wide horizon offer unique experiences. Wind and weather are clearly present. Aircraft flying to and from Copenhagen Airport and ships sailing through the Sound show Copenhagen’s status as a major hub in Scandinavia.

Description of the Intervention
The visions for this project were formulated in the early 1980s by local grassroots and various stakeholders. Openness was to be the predominant quality in the area, and the beachline was to be moved further out to form a better beach. The area was to be a lively landscape for human activity. The gap between the new area and the existing coast was to be maintained in the form of lagoons serving as protected areas for water activities.
Over a period of 20 years, local and regional authorities were involved to an increasing extent, and the project’s individual elements and features were gradually developed. The necessary plans were then prepared and adopted. Once the 200 million Danish kroner that the project would cost had been allocated, the beach could be designed, planned and established relatively quickly. The project was based on an open dialogue with various stakeholders: focus groups, interest organisations and local users were involved in a continuing effort to develop the project’s qualities.
Amager Beach is fully finished with jetties, islands, promenades, paths, dunes, green areas, beach stations, etc. In the southern and central areas of the Beach Park, a number of specially designated areas are available for further development, now under ways.
The architectural structure focuses on the meeting between the linear coastal road and the building lines in the flat landscape of the island of Amager and the new coastline. Long accurate lines of sight go through the beach park and the bridges across the lagoon are important elements in the entire scenography. The coastline is laid out in consideration of the dynamic forces of wind, waves and currents. Three focal points are particularly important in the new landscape: the point at the extreme east that governs the main orientation of the two beaches, and the two delineating jetties to the north and the south. In order to highlight and emphasize the vast landscape, the service buildings on the beach – the “beach stations” – have a special character: They follow the grand lines of the landscape and are designed and laid out as cliffs for people to walk on and around.

The northern beach, the Landscape Beach, is a long peninsular with low dunes. The winding concrete path through the landscape uses small topographical variations to create variety for people walking through the coastal scenery.
The City Beach to the south is different: there are no dunes here. The broad beach and long curved promenade, interrupted by open beach squares, are designed as one large seating sculpture with grassy areas for games and lounging. Behind are the parking areas.